Short answer
Most CRM migrations fail on data quality and integrations, not on the import itself. Clean and map before you move, run a full trial import, freeze the old system for the cut-over, and keep it read-only until reports match.
Before you start
- Choose and contract the target CRM first; mapping depends on its data model. See the CRM selection criteria.
- Name a project owner and a business owner who signs off data quality.
- Agree lifecycle stages and pipeline definitions with sales.
The sequence
- Inventory. List objects (contacts, companies, deals, activities, tickets, custom objects) with record counts, and every integration that reads or writes CRM data.
- Decide what not to move. Stale contacts, duplicates and long-closed deals cost money in the new system and slow adoption.
- Clean. De-duplicate on a unique key (email, domain or external ID), normalise picklists, fix owners.
- Map. Field by field: source, target, type, transformation and picklist mapping. Remove fields nobody uses.
- Plan history. Decide whether emails, calls and notes are imported in full, summarised, or archived as an export.
- Rebuild integrations and automation in the target, in a sandbox if available.
- Trial import. Import everything into a sandbox, compare counts per object, and spot-check 20 or more records end to end.
- Cut over. Freeze edits in the old CRM, run the delta import, switch integrations in a planned order.
- Verify and adopt. Rebuild key reports, compare them with the old CRM for a month, train users by team.
Signals of a higher-risk migration
- More than 100,000 records or several custom objects.
- Five or more integrations writing to the CRM.
- Activity history that must remain searchable.
- Large teams with different processes per region.
The CRM migration planner builds a checklist from these factors.